West Dulwich Street Improvements

UPDATE:

Lambeth council introduced the West Dulwich Street Improvements to reduce road danger and create a safer and healthier neighbourhood where residents can live happier, healthier lives.

The improvements included a trial of traffic restrictions to remove through-traffic, and enhancements to pavements across the neighbourhood.

The trial scheme was launched on 9 September 2024.

A group of local residents and businesses challenged the legal basis of the scheme. Following a hearing earlier this year, the High Court allowed part of their claim and subsequently ordered the removal of the traffic restrictions.

The restrictions, including the signs and cameras, have been removed and that the scheme is no longer being enforced.

Following the court ruling, the council has decided to refund Penalty Charge Notice (PCN) fines issued in relation to the scheme.

Motorists who received and paid PCNs in relation to the Street Improvement Scheme in West Dulwich (from driving through the restrictions at Ardlui Road, Carson Road, Chatsworth Way, Eastmearn Road and Tulsemere Road) can apply for a refund on the council’s website: https://www.lambeth.gov.uk/wdhnrefund. PCNs issued in relation to this scheme that were not yet paid have been cancelled.

In July and August, sections of the pavement that have been damaged by tree roots will be repaired. To keep trees healthy and prevent roots from protruding, the pavement around a number of trees will be renovated with a breathable, flexible material, making the pavements smoother, safer and more accessible for everyone. A map of pavement repair locations is shown below:

Pavement repair locations

Lambeth is committed to creating streets and neighbourhoods that are healthy, safe, inclusive, pleasant, and that support walking/wheeling, cycling and use of public transport. Enabling the community to travel more actively benefits public health and wellbeing, and is part of the Climate Action Plan to become net zero compatible and climate resilient by 2030.

Phases

Phases overview
Baseline Data Collection and Informative Engagement
Baseline Data and Informative Engagement Report
Initial Design Engagement
Initial Design Report
Final Design
Trial Street Improvements Launch

Trial Street Improvements Launch

9 August 2024 - No end date

Stage 6: Trial Street Improvements Launch:

A trial of the traffic restrictions was launched on 9 September 2024.

A group of local residents and businesses challenged the legal basis of the scheme. Following a hearing earlier this year, the High Court allowed part of their claim and subsequently ordered the removal of the traffic restrictions.

The restrictions, including the signs and cameras, have been removed and that the scheme is no longer being enforced.

Following the court ruling, the council has decided to refund Penalty Charge Notice (PCN) fines issued in relation to the scheme.

Motorists who received and paid PCNs in relation to the Street Improvement Scheme in West Dulwich (from driving through the restrictions at Ardlui Road, Carson Road, Chatsworth Way, Eastmearn Road and Tulsemere Road) can apply for a refund on the council’s website: https://www.lambeth.gov.uk/wdhnrefund. PCNs issued in relation to this scheme that were not yet paid have been cancelled.

In July and August, sections of the pavement that have been damaged by tree roots will be repaired. To keep trees healthy and prevent roots from protruding, the pavement around a number of trees will be renovated with a breathable, flexible material, making the pavements smoother, safer and more accessible for everyone. A map of pavement repair locations is shown below:

Pavement repair locations